Three quotations arrive for ten office chairs. Supplier A lists TZS 85,000 per chair and TZS 60,000 delivery. B lists TZS 91,000 per chair with delivery included. C lists TZS 84,000 per chair with delivery included but gives a lead time of 12 working days. Your exercise requires delivery within seven working days.
Build a comparison sheet
A and B both cost TZS 910,000 delivered. C costs TZS 840,000 but misses the stated deadline. Record the chair specification, quantity, tax treatment, lead time and quote validity in separate columns. The example assumes the totals are comparable on tax. If a quotation is unclear, flag it for clarification before comparing totals.
Write the recommendation
If A and B meet the specification, compare documented delivery commitments, warranty and other approved criteria. Example: “A and B tie on delivered cost. A confirms five working days and B confirms seven. Recommend A if delivery time is an approved deciding factor.” Keep the original quotations and record who approved the decision.