A project has TZS 600,000 approved for a workshop. A venue booking commits TZS 220,000, refreshments already cost TZS 170,000 and transport quotes have arrived but are still awaiting approval.
Show three distinct figures
Record approved budget, approved unpaid commitments and posted actuals. With TZS 220,000 committed and TZS 170,000 already spent, TZS 210,000 remains before any provision for unapproved transport. List pending quotes separately so they are visible in planning discussions.
Avoid counting the same expense twice
When the venue invoice is posted, move the corresponding amount from commitments into actual expenditure. If it posts at TZS 230,000 following an approved change, available budget becomes TZS 200,000. Keep the activity code and supporting document reference on each line. Review unresolved commitments after the event and close them under the project procedure.