Your team budgeted TZS 300,000 for transport and spent TZS 360,000. A report that says “transport costs increased” gives the manager very little to work with. Explain the change using records you can verify.
Break the difference into causes
The overspend is TZS 60,000, or 20% of the budget. Suppose the budget assumed 10 trips at TZS 30,000 each, while the actual record shows 12 trips at the same rate. The full difference comes from two extra trips. Check whether the extra work was approved and whether it is expected again.
Name the next action
Try: “Transport was TZS 60,000 over budget because two additional deliveries were required. The trip rate stayed at TZS 30,000. Operations will confirm whether the revised delivery pattern will continue next month.” If spend reflects a bill posted in a different period, explain the timing and identify the document that supports your account.